CJ20N v CJ20 (Adding to an existing structure by copying from a template)

Former Member
0 Kudos

Hi

CJ20 supports adding to an existing structure by copying from a template.

This can be done by clicking on the WBS Basic Data tab and then following the menu path:

Project > Copy From

You can then copy from a Template or Operative Structure.

I have tried to find this really useful functionality in transaction CJ20N - Project Builder however it does not appear to exist.

Does anyone know how this can be done using the project builder.

Thanks

Ian

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

In CJ20N right click on WBS and then click "include". You will find the same screen. Another way to include structure is in CJ02.

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

In CJ20N select the WBS element right click on it select include > WBS element u will get the same window.