Hello Experts,
To use t-code CJCS display change documents: referance WBS, what are the necessary settings that need to done.
Can anyone please give some suggestions.
Thanks in Advance
Sandeep
Dear Sandeep,
Enter OPSA transaction for Project Profile.
Click on Control Tab
ChangeDocuments check box must be Ticked Use this indicator to specify that change documents should be created for all basic data in the work breakdown structure.
Then in same Control Tab go to Status Management subscreen.
Here also ChangeDocuments check box must be Ticked You use this indicator to determine whether change documents are created for the status of a project definition and WBS elements.
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sandeep,
Firstly thanks for your suggestions.
But i have checked in the project profile , the setting you mentioned is alreday in place.
I tried to create the project with the same profile , save and then made some chnages and again saved.
After which when i checked the CJCS..it says no document found.
Anything you to suggest on this please let me know.
Thanks and regards
Sandeep