schedule finish date

Former Member
0 Kudos

Dear Gurus,

In my current system, I am using activity elements with in the activity to plan my resources.

The activity elements take the start and finsih date (earliest) from the parent activity.

Now, during partial confirmation of the activity, I enter the forecast duration to get the next realistic finish date of the actvity. Now when i reschedule my project, the activity element's finish dates are exceeding the parent activity's finish date by one day. The noteable difference i can see before and after the confirmation and schedule update is that, the execution finish time before confirmation was 24:00:00 and after confirmation, its 00:00:00 of the next day of the activity finish date.

For example

Activity finish date is 03.08.2009 with execution time 24:00:00

Activity element finish date is 04.08.2009 with execution time 00:00:00.

Regards,

VDS

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

prob solved

Former Member
0 Kudos

Hi Rupesh,

I don't think there is any difference... 03.08.2009 - 24:00:00 is Midnight of 03 and 04 whereas 04.08.2009, 00:00:00 is same as that of the earlier one (i.e... midnight of 03 & 04) ... Where is the difference of one day ... if it is 04.08.2009 - 24:00 then what you have said is correct..

Regards,

Bala