Dear All,

How to manage the asset in PS. Any document or flow inputs?

Thanks,

Bekele

Accepted Solutions (1)

Accepted Solutions (1)

stheurkar
Active Contributor
0 Kudos

Hi,

1) search "Capital projects" thread in PS Forum.

2) Refer below link which might be useful.

http://help.sap.com/saphelp_46C/helpdata/EN/2a/f9fefd493111d182b70000e829fbfe/frameset.htm

Follow menu path

Investment Management (IM) > Measures (Orders/Projects)

Sandeep

Answers (2)

Answers (2)

MohanDesai
Active Participant
0 Kudos

OK

Former Member
0 Kudos

Hi,

In the investment Project When you Release the WBS carrring appropriate investment profile at that time system creates AUC.

At the first time Settlement of AUC carrying WBS Element system automatically creates settlement distribution rule. After the first time settlement of AUC carrying WBS element you can find the same in in WBS settlement distribution rule.

For the final seetlement ot fixed asset we create fixed asset via T code AS01.

After creation of Fixed asset via AS01. We maually maintain Cj20n -->Ctr+F3 (settlement distribution rule for the AUC carring WBS for which frist seeltment has run and sys. has generated AUC )

In second settlement T code CJ88, sys settle cost of AUC to Fixed asset.

The same can be view after settlement in T code AW01N with the acquivision value of settlement.

Regards

Muzamil