While running CADO (time sheet data) report for employee, data is not being pulled up for the WBS Element and Project Definition. What could be the reason? Here time is entered against a network activity but for some entries WBS element and project definition is dispalyed and for remaining it is not.
Yes....these activities are assigned to the WBS element in the project. As I mentioned earlier for the same activity in some cases WBS element is populated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
please check whether all the network activities are assigned to the wbs elements