Dear Gurus,

There is a customzing point under Project System -> Costs -> Planned Costs -> Maintain plan data handling profile.

Does anyone have any idea about:

- where can it be used?

- what is it used for?

I was looking for any tool which makes plan figures on WBS elements out of purchase orders and I found this but there is no info at all, no where.

Thanks in advance,

Jeno

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This profile is aimed to be used in transaction AD31 (and associated Tcode AD32). Those belongs to an add-on of IS A&D solution.

The purpose is to provide a functionality to calculate the plan cost at completion by adding the actuals costs (including or not the commitments form PO and/or PR) to the cost to complete entered in a specific planning version.

This functionality can also be used to calculate the cost to complete by calculating the difference between the plan costs at completion stored on a dedicated planning version, and actuals costs (including or not the commitments form PO and/or PR).

As SAP provides, independently, the possibility to copy actual to plan, the profile gives the flexibility to calculate the cost to complete by adding 2 planning versions.