PM: Task list attachment not carried into the PM order

Hello,

I attach a document to a PM task list (for example a pdf file). When the system creates a PM order based on this task list (using Maintenance Plans and Shceduling for Maintenance Plans), the attachment is not carried into the PM order (the attachment list is empty)

The same happens if a create a note instead an attachment...

Is this normal or I miss something??

Thankyou very much in advanced.

Jordi Palau.

Former Member
replied

Hi,

It's normal. Any attachments with the task list will not be transfered to the order.

From the orders PLANNING tab you can select and display the task list. Now attachments to the task list can be seen.

-Paul

Please use [Enterprise Asset Management (EAM)|; forum for PM/CS specific topics