CAT5 : transfer to project system

Former Member
0 Kudos

Hi ,

Pls tell me how CAT5 works,

where can u c the result of the same.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Prerana,

Though your qn. is not very specific... this is the way CATS works,

First you have to book the time in the project by making an entry in CAT2 using Data Entry profile & Personnel no. After that it will be approved by the concerned approving authority using CATS_APPR_LITE then it will be transferred using CAT5. You can see the results using CATS_DA.

Regards,

L.Balachandar

Answers (6)

Answers (6)

Former Member
0 Kudos

Thanx the issue is closed

former_member711289
Participant
0 Kudos

Hi Prerna,

Is your query solved? If yes kindly close the issue.

With Regards

Abhishek Sinha

Idhasoft, India

former_member711289
Participant
0 Kudos

Hi Prerna,

In cats employees book their time sheet in cat2. after that these timesheet are approved by project manager in cats_appr_lite. after that thru cat5 cost of these timesheets are transfered to project. if u wanna see the the effect of cat5. in ur project u can see the report planned /actual thru and there are several report where can see the planned and actual figures . In this report actual cost is coming via cat5. one std report is s_alr_87013531. check this.

Regards

Abhishek Sinha

Idhasoft, India

Former Member
0 Kudos

Hi Prerna,

Edited by: robo robo on May 9, 2009 1:50 PM

Former Member
0 Kudos

Hi,

if u have booked time for network activity with work center ,activity type in CAT2.

Then after CAT5, the actual cost will be posted against the WBS element.

which u can see in the CJI3 report, for that wbs element.

Ashis

former_member203108
Active Contributor
0 Kudos

CAT5 will confirm activities in PS...for more information pls refer http://help.sap.com/saphelp_erp60_sp/helpdata/en/64/400b2b470211d189720000e8322d00/frameset.htm