on 05-07-2009 12:25 PM
Dear All
I have creat activity type & assign this activity type to work center in "ActTypeProc." IN KP26 , i maintain activity price & all other things but when i maintain this activity type & work center in WBS for respective internal activity system not shown me plan cost as well as when i confirm the activity system not shown me actual cost also. Pl gave some input on this
Regards
Hi nivruti,
check ur work center whether u have put formula sap008 in other formula in capacity tab page. in schedulling tab page formula sap004 . check whether in costing tab page ur entries are correct regarding activity type and cost center.
In activity type put * in cctr catagory , activity type catagory 1, give secondary cost element (this can b a reason of ur problem) in allocation cost element.
Apart from this also check costing variant whether actual and planned has been maintained properly or not.
Regards
Abhishek Sinha
Idhasoft, India
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check in OPSU whether you have ticked the Cost checkbox for Control Key PS01.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.