cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Type

Former Member
0 Kudos

In BoM, the header material with MRP Type:M0. Should I maintain the components with the MRP Type in MPS category (like M0, M1, M2, M3 and M4) or can I use PD for other componets? How will it function in both cases?

Rex

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please refer my reply from this link,

[MPS and MRP|]

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

When running MRP using transaction MD02 and MD41, what the difference should be?

There is no difference in the processing logic as such. The only difference is that MPS only acts on materials with an MRP type relevant to MPS (e.g. M0, M1, etc...), and MRP acts on materials with an MRP type relevant to MRP (e.g. PD). How the materials are processed is exactly the same.

This functionality allows you to run MRP for 2 sets of materials separately (and with a different frequency).

For example, some businesses may do planning for their finished goods once per week, but would want to run MRP for their

components daily (although this is generally not necessary with SAP). So, for this example, you would define all finished goods with an MRP type relevant for MPS, and all components with an MRP relevant.

Basically, MPS is a form of MRP that concentrates planning on parts or products that greatly influence the company profits or those that require critical resources. Items marked as master schedule items can be finished goods, assemblies or raw materials. These items are selected for separate MPS run that takes place before the MRP planning run. MPS run is executed without any BOM explosion. This is to allow the MRP controller to ensure that the master schedule items are correctly planned before any detailed MRP run take place.

Regards

Krishna