Error message : No order corresponds to selection criteria

Former Member
0 Kudos

Hi,

I am using T code CN24N for scheduling networks for a project and entering Project as the input.

But I am getting the error:

No order corresponds to selection criteria

networks are there for the selected Project.

Can anyone tell me the possible reason for this?

Regards,

B P Singh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I got the solution

nitin_patoliya
Active Contributor
0 Kudos

Request you to share the solution with forum.

With Regards

Nitin P.

virendra_pal
Active Contributor
0 Kudos

Hi Nitin

you need to set up levels in network to run this transaction.

Regards

Virendra

nitin_patoliya
Active Contributor
0 Kudos

Virendra,

Thanks for you input, Please clarify in detail. By setting up level in Network you mean to say use of subnetwork.

With Regards

Nitin P.

Former Member
0 Kudos

Dear Experts,

                      Can anybody Share the solution for this error .".No Order Corresponds to Selection Criteria"

Thanks in advance,

By

Suma

Former Member
0 Kudos

Hi,

Specify the Project & Network for the project in selection creteria & select the option as only selected network & excute the transaction.

Regards,

Raj

Former Member
0 Kudos

Hi,

Still getting the same error.

Regards,

Former Member
0 Kudos

Hi

Please choose right DB Profile.

eg.000000001 is default... check weather there is some more configured profiles.