One Project Multiple Company codes

Former Member
0 Kudos

Dear All,

I want to create one project and Assign 4 company codes like aaaa, bbbb cccc dddd, Is it possible

and If I can do that , How is it possible to control the budget for individual Budgets of the company

code

With Regards,

kamal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Kamal,

The best way is to do the following thing

1. Make 4 Root level WBS.

2. Don't assign any company code in the project defination.

3. Do the budgeting on the basis of the controlling area

4. Release the budget

Hope it will work

Uddhab

Former Member
0 Kudos

1. Make 4 Root level WBS.

2. Don't assign any company code in the project defination.

3. Do the budgeting on the basis of the controlling area

4. Release the budget

1. 4 root level WBS not clear please do help me?

2. Second point is clear

3. do the budgeting on the basis of the controlling area , In our company 1cost center = 1wbs element?

4 forth point is also clear

With Regards,

kamalnatham

Answers (3)

Answers (3)

Former Member
0 Kudos

In addition to above in OPS9 (Budget Profile) under availabity control chk the box for Object currency , this will work.

I was having same scenario and tested it few days back.

Thanks

Sarang

Former Member
0 Kudos

In addition to above in OPS9 (Budget Profile) under availabity control chk the box for Object currency , this will work.

I was having same scenario and tested it few days back.

Thanks

Sarang

Not clear , Please give me some more information

Former Member
0 Kudos

Hi

At the time of creating project , u can change the company code in the wbs , and the currency will be determined from the company code.

when u ll do planning, then select object currency, so that u can plan for individual wbs with different currency, but in report you will see in controlling area currency.

Pre req.----select object currency in planning profile

maintain exchange rate type

ashis

Former Member
0 Kudos

At the time of creating project , u can change the company code in the wbs , and the currency will be determined from the company code.

when u ll do planning, then select object currency, so that u can plan for individual wbs with different currency, but in report you will see in controlling area currency.

Pre req.----select object currency in planning profile

maintain exchange rate type

Dear ,

So when I am creating the project, I will not give the company code and u mean to say I need to give

company code at the time of WBS cretion level

and When i am doing Planning I need to select Object currency

With Regards,

kamalnatham

nitin_patoliya
Active Contributor
0 Kudos

Project can be executed across company code... But the controlling area is one.

For this type of requirement you can create 4 level 1 WBS and assign the same to One P.D. , In P.D. don't give Cocd.

Regarding budget, commitment managment we are activating at COAr level and not Cocd level..

Regards

Nitin P.