I have sales order, which line item 10 material X, which is no more stock so its proposed item Y in line item 20 say 12 Nos.

deliveried 5 quantity is dec 2008, and deliveried 5 quanity in march 2009, remaining balance quanity is 2.

Now user dont want to delievr 2 quanity, and item status present is being process, but user want it to be completed.

when i check in sales order item 20, its greyed out and all shedules lines also greyed out.

If you ahve any idea, to remove 2 quanity in sales order and line item status to make completed.

Regards

Ramki

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Not able find soloution

Former Member
0 Kudos

hello, friend.

if there is an existing delivery for the balance of quantity 2, then you could not enter a reason for rejection. if this is so in your case, you need to delete that delivery item (if part of a larger delivery document with other items) or you could delete the delivery. doing so frees the order for the entry of reason for rejection.

regards.

Former Member
0 Kudos

Hello Friend,

Try to make use of reason for rejection for that particular order then try whether it satisfies your requirement.

Former Member
0 Kudos

Hi Sunil,

That feild also in grey mode.

Regards

RAmki

Former Member
0 Kudos

Hello,

In our system we go to item level select schedule line tab then select non-confirmed ordered quantity in Order quantity column we enter 0 to complete the sales order.

If you system shows totally grayed out in schedule line tab then you company modified USEREXIT_FIELD_MODIFICATION in MV45AFZZ.

Or Try with user exit FORM USEREXIT_SET_STATUS_VBUP in the include RV45PFZA.

regards

rc gopi