How can i avoid transport requests to be displayed in Prod-system before QA

Hi,

we have established a QA-process in our TMS and it works fine, but i wonder if this behaviour is normal:

when a request is imported into QAS, it appears as an inactive request in the PROD-queue, too.

I understood the QA-process that only approved requests will appear in the import queue of PROD. Is there a setting that we have to change to let only approved requests appear in the PROD queue?

Thanks,

Valentin

Former Member
Former Member replied

Hi Valentin

This is the normal working status. As soon the request is imported in

QA system, the buffer entry is added by the import process itself to

the target system in the delivery route.

Please refer to the note 313991 for the solution to import the only the

approved requests. You need to do recommended changes and schdule the

job to move the requests.

Kind Regards,

Aidan

0 View this answer in context