Did you mean: 

Valid from date of Inspeciton Plan

Former Member
0 Kudos

Hi experts,

Are we able to change the valid from date in the inspection plan for an existing counter ?

Regds

jomy

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jomy

It is not possible to change valid from date in the inspection plan for an existing counter ,

you can change the existing plan but the new key date will appear in the header of the plan as changed on date

can you explain little more about the scenarion why this requirement is generated? so that we can think over from your requirement point of view.

Thanks

Vinay

Former Member
0 Kudos

Hi,

This is for some printing requirement of Inspection plan. (of valid from date of Inspection plans)

The scenario is that some changes in the Inspection plan details requires the validity of Inspection plan to be changed for printing

But changes in some other details will not require the validity change revision. There fore I cannot base on the changed on date for the printing requirement.

I think the best way is to create a new counter for the plan and delete the old one when the first scenario happens.

Regds

Former Member
0 Kudos

Hi Jomy

It is not possible to chnage valide date for a gr counter.

All you can do is create new gr counter from different date or delete or archive original on bt QSR6 T code.

Regards

Sujit