Dear Gurus,
I am facing problem while doing time sheet booking at WBS ELement. System gives error "Budget exceeded for the WBS (Error no:BP 603)"
The steps I follow are as under:
1. I created a project in CJ20N
2. Budgeted the project in CJ30
3. Released Budget in CJ32
4. The settings of the budget profile are such that when I release the budget, Availability Control gets activated.
5. Released the project
6. In CAT2, I post actual hours and give reference of the reciever WBS of the project.
Now, in CAT7, when I try to transfer to CO, system gives me the error:
"Item 001 WBS xxxx BUDGET EXCEEDED (error no. BP 603)"
Same thing happens if I try to settle a work order on the WBS and any FI posting
But it allows to post costs for Goods issue.
In tolerance limit settings, the usage is 100% and "All activity grps " is selected
Regards,
VDS
you can check whether budget is available for particular WBS Transaction S_alr_87013558
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It seems to be the budget is increased once ur doing CAT7.. so increase the Budget in the WBS element and try to post it again..
I hope this is the problem
- Pithan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|