Network Costing

Former Member
0 Kudos

Hi All

Can someone tell me why for what resons

when i Run CJ9K

The Network Costing does not Happen.

This Happened Only in the Case of one Project.

Thanks again for yor Help.

Mercy

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

Hi...

Go through this link...http://help.sap.com/saphelp_erp60_sp/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm...and check whether u fulfill the prerequisite for running CJ9K

Former Member
0 Kudos

HI

Can U Let me Know the Pre-requistes

For some reason I am unable to acess the link

Thanks

Regards

Mercy

former_member203108
Active Contributor
0 Kudos

Asynchronous Network Costing

Use

You can use the asynchronous network costing to:

Update the network costing

Reproduce plan payment data in Project Cash Management

Have the system value configurable materials per the configuration settings entered

Refresh the purchase info record data for goods and services procured externally

You can run the asynchronous network costing for one or more networks at any time, regardless of the costing in network maintenance.

Prerequisites

The network must be activity assigned.

Project Cash Management must be active, so that the system can determine and update the payment data.

To have the system value the configurable materials in line with configuration, you must maintain an appropriate costing variant for the network.

Features

You can use the asynchronous network costing to calculate or update the plan values for several activity-assigned networks simultaneously. The system determines and updates the following values:

All planned costs (similar to the network costing within network maintenance)

Planned outgoing payments (if Project Cash Management is active)

Costing for configurable materials in valuated project stock, per the configuration settings entered

If you have set the Read purchasing info records indicator, the system updates the purchasing data for externally processed activities and non-stock materials.

Overhead and process costs are also included as part of network maintenance.

If errors messages occur during the network costing, the networks concerned are not updated.

Former Member
0 Kudos

Hi,

The CJ9K Network costing will run in case of the Project only.

The network defined should be assigned to project.

If the Network is individual then it wont run for network costing.

Regards,

Raj

Former Member
0 Kudos

Raj,

The Network is attached to the Project.

But The cost is not updating

Thanks

Regards,

Mercy