on 05-06-2009 7:54 AM
Hi,
I have made service PO and made some service entry sheets in it. Now i want to close the PO, i.e, its committment should become zero. How can i do it. i have already made service entry sheets and accepted it, so now i dont want to make any SES in which i can give "final entry sheet" indicator. How can i close that service PO without making final service entry sheet. System is not allowing me to make SES with zero quantity so that i can mark it as "final entry sheet".
Regards,
Kalpesh Agrawal
Hi Kalpesh,
I think you need to select the po line item and block(lock symbol) the same.It should reverse the commitment,i am not sure pls check
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kalpesh,
Once you block/delete the line item in PO system will not allow you to make any transaction against that line item. Similarly whenever you click on delivery complted indicator system will always allow you to make GR/SES against the PO. By delivery completed indicator only thing is that it will not consider the same in any report/net calculation.
And you can make the field delivery completed available by making it optional in PT9F in screen display.
I had just checked the same.
Regards,
Umesh Agrawal
System will block doing MIRO only for the particular line item.You have two options.If you can do the invoice posting now then do it and then block the line item.Otherwise if you do not want to post the invoice now and also you do not want anyone to do service entry sheet then you block the line item and whenever you plan for invoice posting unblock the line item and after posting the same again block it.
If the Service Entry Sheet is to be cancelled then go to ML81N and Select PO / SES and Click on "Change" Mode and Go to Menu Service Entry Sheet --> Set Status --> Revoke Acceptance.
The Procedure is Same for Cancelling the Release.
For Deletion of SES Press Shift F2 or Menu Service Entry Sheet --> Delete & Save.
Prashant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Make the quantity of the service line item in PO equal to that of actual qty consumed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I would suggest you to check the following notes:
772206 - Commitment Update in Service Purchase Orders:
In case of valuated goods receipt
o when a Service entry sheet is accepted.
- The Purchase Order commitments can be completely reduced by
setting the delivery completed indicator, see note 735404.
In case of non-valuated goods receipt
o when an invoice is posted.
- The Purchase Order commitments can be completely reduced by
setting the final invoice indicator.
The case of non-valuated goods receipt and unplanned multiple account assignment in invoices
is described in note 496557.
The delivery completed indicator in the purchase order
(EKPO-ELIKZ) is by default hidden ON PURPOSE for service items so
that the control is not performed in the purchase order, but
indirectly via the final entry sheet indicator in the respective
entry sheet.
You can show the delivery completed indicator for the PO in the Customizing for screen layout, find out the field selection keys according to note 30316 (SPRO->MM->Purchasing->PO->Define screen layout).
Please check first for reference key PT9F (the one used by services)
the flag "delivery completed" - is it hidden? - then set it to
optional and you can set in the PO item EKPO-ELIKZ to x. I would advice you to check the table COOI for the PO afterwards.
Regards,
Edit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
If you want to make commitment Zero then you may have to cancell the entry sheets already created no choice before you you have to visit the ML81N screen again. But if you do not want to have further SES then Use the lock indicator for the service PO item/s in ME22N mode , check out the delivery tab, in that you will find a field Latest GR date enter current date or any other date you wish and save the arrangement. You need not go to the SES screen tocarry out the closing activities.
Regards
Edited by: samuel mendis on May 6, 2009 9:08 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
go to ML81N and rovoke all service entry sheets you creaed.
goto ME22n and delete the line item by, select the line item and click the delete button,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.