Former Member
0 Kudos

We have tried to copy a project from one CO version to another using transaction CJ9B, but it only copies to the WBS element level. Is there a transaction that will copy a project to a different CO version that included components down to the activity level?

Thanks, Rae

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

during copying from simulation version, actvity level cost will be copied, but not in co version.

ashis

Answers (3)

Answers (3)

Former Member
0 Kudos

Try CJ9F also...

Sarang

former_member203108
Active Contributor
0 Kudos

Try using Tcode...CJ9FS

Former Member
0 Kudos

In Cost Planning for CO version 0 (Plan version 0) in CJ40 you are planning costs at WBS level, not at activity level.

So where the question of copying activity cost come?

Activity costs come at activity level planning, not in plan version level.

Which as mentioned can be copied by simulation version, project version.