on 05-05-2009 8:00 PM
Hi All,
in PRD XI Server i have two interfaces running based on the CC Scheduling(Avalability of Times)
Interface1 shld be run every day at 11:15pm To 11:55 pm and shld stop automatically
There after Interface2 shld be run at 12:00am To 11:00 pm and shld be stopped automatically
This is daily process running and processing fine.
Today morning at 10:00am unexpectedly i Started the Interface1 which shld not run this time.
And also i Stopped the Interface2 that time.
by starting the CC itself Interface1 ran for 3 files and processed.(Because both channels r polling the same DIR with same file name)
Now i stopped that CC of Interface1 through Runtime workbench and started Interface2, now Interface1 stopped and started the Interface2 also, Now the Interface2 in in Progress and running
As of now Interface1 is stopped and Interface2 is running
My Doubt is will this Interface1 can be Invoke automatically at 11:15pm today??
And also will be the Inteface2 can be stopped automatically at 11:00pm of today??
Plz suggest me
Regards
Edited by: Vamsi Krishna on May 5, 2009 9:07 PM
Edited by: Vamsi Krishna on May 5, 2009 9:08 PM
The answer to both the questions is Yes.
Regards,
Prateek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We had the similer problem 2 yrs back. We didn't face any issues at the time
No Problem in your case... The Interface2 will be stopped and Interface1 will start automatically. The Scheduling will be taken from the central server timings. Unless you change the system time, every thing will be perfect.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
76 | |
9 | |
8 | |
7 | |
6 | |
5 | |
5 | |
5 | |
5 | |
5 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.