on 05-05-2009 1:36 PM
Hi friends,
Please help.
When I want to convert planned order to purchase requisition in MD04 system do not assigne internal number.It ask for external number range.I want system should propose internal number when I convert Planned order to PRs.
How to achieve this.
Edited by: Raja on May 5, 2009 2:36 PM
Dear,
You need to define the number range in OMDN and assign the number range in OM12/OM13 at plant level.
you donot maintain the number range here, system will take the data from PR document type which you have maintained in OMEB.
Else you can directly maintain uder the number range tap of OPPQ for plant or OPPR for mrp group.
Hope it will work for you.
Regards,
R.Brahmankar
Edited by: R Brahmankar on May 5, 2009 6:51 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.