In the Actual Costs field the data is flowing from Actual Work x Rate given in kp26 or something else also will be there?

Bekele

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Bekele,

Actual cost comes through different ways depending upon your type of activities. i.e

1. For Internal Activity

1.1. From Capacity Assignment - WORK * Rate defined in KP26

1.2. From Store (if integrated with MM and materials are reserved with activity), cost will occur after good receive.

2. External Activity (External procurement process --- PR >> PO >> GR

3. Service Activity -


PR >> PO >> Service Entry Sheet

4. Cost Activity -


Direct cost booking using FB60

Sum of all these costs is shown in CNE5 report.

Regards,

Murtaza

Answers (2)

Answers (2)

MohanDesai
Active Participant
0 Kudos

Thanks

anishpv
Participant
0 Kudos

yes it will take only values given in k26