Budget check in PM Orders

Former Member
0 Kudos

Dear Experts,

When I am trying to save Maintenance Orders after including reservations (in PM Module) which are raised against WBS Elements , I am getting an error specifying u201CError occurred during budget check, see cost protocolu201D.

Need your guidance to sort-out this issue.

Thanks in advanced,

Dileepa,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

In ur maintenance order in header menu GOTO >logs > cost determination check the message for by wht amt budget is exceeded.

Rgds

anishpv
Participant
0 Kudos

Hi,

Since you are linking WBSE to Maintenance order,cost of the order is controlled by the WBSE.

Check the Budget Release value in CJ33.

Supplement Budget CJ37 by the exceeded value and do Budget Release (CJ32)

Exceeded value can be obtained as told by Rasam

regards

pv

Answers (2)

Answers (2)

nitin_patoliya
Active Contributor
0 Kudos

As your PM order is assigned to WBS. And WBS is not having suffiecent budget. Please provide additional budget to WBS.

Regards

Nitin P.

Former Member
0 Kudos

Is the WBS assigned to PM Order on Additional data tab?

If yes, then chk the tolerance limits on WBS. The total cost on Order is exceeding the budget of WBS.

Thks

Sarang