Hi All,

I did a forecast based planning for a material.

I completed all the process and ran MD04.

In MD04 i am seeing MRP Element as FORREQ.

How can i convert those forecast req in to PR's.

Kindly help me in this regard.

Regards

KK

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

KK,

Now run MRP (MD01 or MD02).

FOREREQ is a 'requirements' element. MRP will perform its calculations, and as a response to the requirement, will create a proposal, which will be a 'supply' element. If your material's procurement type is 'External' (purchased), then the proposal will be a purchase requisition.

[MRP Procedure|http://help.sap.com/saphelp_erp60_sp/helpdata/EN/f4/7d252f44af11d182b40000e829fbfe/frameset.htm]

Regards,

DB49.