如何限制计划交货数量不超过目标数量?

Former Member
0 Kudos

在scheduling agreement的操作过程中,如果计划交货数量(scheduled quantity)是由MRP产生的,就会出现计划交货数量超过目标数量(target quantity)的情况。 请问如何限制?谢谢!

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I will test soon. Thanks to all involved.

Former Member
0 Kudos

sorry but this is standard behavior as described in note 83343.

MRP don't check target quantities.

The planning run should run automatically and should not be interrupted

by some events. The system makes a decision either in favor of the quota

arrangement or in favor of the source list. The system reads the

scheduling agreement once in the update process. To have a check on

the target qty would require another read of the document which was

determined to be detrimental to system perfromance.

A maximum quantity can be considered by means of the quota arrangement.

Please see the attached note for more information.

83343 *** MD01: No check of target qty in sched. agreemnt