on 05-02-2009 2:07 PM
在scheduling agreement的操作过程中,如果计划交货数量(scheduled quantity)是由MRP产生的,就会出现计划交货数量超过目标数量(target quantity)的情况。 请问如何限制?谢谢!
I will test soon. Thanks to all involved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry but this is standard behavior as described in note 83343.
MRP don't check target quantities.
The planning run should run automatically and should not be interrupted
by some events. The system makes a decision either in favor of the quota
arrangement or in favor of the source list. The system reads the
scheduling agreement once in the update process. To have a check on
the target qty would require another read of the document which was
determined to be detrimental to system perfromance.
A maximum quantity can be considered by means of the quota arrangement.
Please see the attached note for more information.
83343 *** MD01: No check of target qty in sched. agreemnt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.