is it possible to create final assets automatically in PS when project is released or some other predefined stage(like creation of AUC)?? we need to create AUC & Final Assets both automatically. pls explain how it can be configured..
regards,
Sam
AuC can be created automatically by selecting manage AuC check box in the Investment profile attached to the project WBS
To create final asset automatically there is BADI, but this is in FI-AA scope
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in Transaction OPSA
in controlling Tab,select the investment profile Model with line item settlement of AuC or you can define new investment profile in transaction OITA.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.