on 04-30-2009 2:38 PM
Hi
Project Systems report S_ALR_87013558 is duplicating Commitment and Remaining order Plan values as a result that WBS element it consume budgrt twice .
I tried to run CJEN to update info Database but still it didn't help. Can you please help.
Regards
Sandile
Try Program RKANBU01
Regards
Sreenivas