Hi,

I have an issue while changing a Sale Order. When I clear a particular block in VA02, the manual pricing conditions that were entered in VA01 are deleted and document becomes incomplete again. This happens only to the child material in a material determination scenario. This happens only for that particular block and that too only when I clear the block. If I change the block, there is no such problem. What I would like to know is,

1. Can this error be trigerred from a configuration/setting?

2. Or is there no such possibility of such error happening that it has to be from some user exit?

I tried manually overriding the error, but it didn't work out.

Kindly help me in this issue.

Thanks in advance,

Poornima L Nathan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

by the description provided , it seems that a user exit is used to have a repricing done when the delivery block is removed . this repricing might have been with type b , do a complete repricing

hope this helps

Thanks

akasha

poornimal_nathan
Explorer
0 Kudos

@ Doss: I mean a Delivery Block in the Sale Order Header

@ Akasha: i've checked all the user exits. There is no such code.

Can anyone tell me at what times can a pricing be carried out again in a Sale Order?

Former Member
0 Kudos

Hi

Pricing can be carried out again in sales order:

1) if you change order qty.

2) If you manually do.

Former Member
0 Kudos

What kind of block you mean in sales order?