Dear MM Gurus,
In the SAP Solution provided for my customer, changes are allowed in prices/quantities of a PO even after the PO history is build (after GRN). I think this conceptually wrong. Is there a control we can impose in Configuration.
Cheers
D_
You have to go through the SAP Note- 457511- PO change & GR , You will find the details of your query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can have a release strategy with changes not possible after release.
Regards,
Prabu