Hi!
how do i enter budgers for statistical internal orders?
Can i enter budgets by cost element for each internal order?
Yes you can. Use KPF6 for manual planning. If you want to use excel-integrated planning, you need to configure planning layout, allow integrated planning on the order type, in the order master data and on the controlling area.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Don't mix planning with budget; budget could be entered only on the level of the internal order itself (no matter statistical or not), but not on the level of cost element. Planning, on the contrary, could be done on this level as well.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.