how do i enter budgers for statistical internal orders?

Can i enter budgets by cost element for each internal order?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Yes you can. Use KPF6 for manual planning. If you want to use excel-integrated planning, you need to configure planning layout, allow integrated planning on the order type, in the order master data and on the controlling area.

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi,

Don't mix planning with budget; budget could be entered only on the level of the internal order itself (no matter statistical or not), but not on the level of cost element. Planning, on the contrary, could be done on this level as well.