Backflush and BOM Quantity.

Hi

I have created BOM for FG and define ROH in that and ratio is 1:1

Then I have created Production order system calculated the Comopnent quantity correrectly.

But in CO11N while backflush good movement system taking less quantity.

Why the system is picking only 120 nos component when the finish item is getting confirmed for 198 ?

I don't have any component scrab or assembly scarb etc.

Please guide me

Regards,

Manish

Former Member
replied

Dear,

Please check user may have deleted quantity from component screen.

Also check the setting of COB1 and MBC1 for batch split.

Regards,

R.Brahmankar