upgrade from 3.5 to 7.0 (RSMDCNVEXIT)

Former Member
0 Kudos

Hi

Is it absolutely neccessary to run transaction RSMDCNVEXIT (Converting Inconsistent Characteristic Values) before the upgrade.

Our system status says 'all characteristics has correct internal values' so i am not sure we need to bother with this as our system is not the biggest anyway.

If i was going from 3.0 to 3.5 then I would definately do it of course but from 3.5 to 7.0 i am not too sure.

regards

goawtason

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Goawtason,

You can skip this test. We skipped this stpe and we have yet not faced any issue. All data loads to master data are working fine.

But carry out other steps for master data consistency mentioned in the upgrade guide.

Regards,

Niraj

Answers (2)

Answers (2)

ChandranGanesan
Active Contributor
0 Kudos

Hello Goawtason

You can skip this test as its not mandatory one. We did the same when we went for BI7.0 from BW 3.5.

See this for more details - Note 447341 - values for ALPHA conversion routine

Thanks,

Chandran

Former Member
0 Kudos

Hi goawtason,

check this upgrade guide:

[SAP NetWeaver 7.0 BI Upgrade Specifics|https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/10564d5c-cf00-2a10-7b87-c94e38267742]

Regards

Andreas