Hi PP Experts,
1.what will be the best time for capacity planning,
after planned order or production order?
2. can we give oeration wise quantity in routing
eg. in operation 0030 qty 100
operation 0040 qty 40
like that......
3. can we splitt the order quantity in routing?
Thanks
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Best option is after convertion of planned order to production order. Because if you do the capacity planning of planned order and then convert to production order then scheduling date will get change .
You can define the routing with releation to base quantity.
Please refer my reply from this thread,
Hope clear to you.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.