cancel
Showing results for 
Search instead for 
Did you mean: 

Scheduling

Former Member
0 Kudos

Dear all,

I have an issue in scheduling.

After MRP Run , the results of are as follows:

Sched St Sched Fin

FG 13.05.09 14:00 13.05.09 17:30

SFG 12.05.09 09:00 12.05.09 17:30

Whereas, system always schedules SFG Prodn Order backwards only from previous end of the day - 12.05.09 17:30.

Here , I want the SFG production order to be finished just sometime (say,30 min) before FG prod Order start time u2013 13.05.09 13:30 Hrs .

ie, SFG backward scheduling shd start from FG start date/time.

Is this possible?

Regards,

Sheik

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Got reply from SAP that this is as per SAP std only.

Regards,

Sheik

Former Member
0 Kudos

Try to maintain inhouse production time as zero and float after production for SFG as zero & see if it works.

Former Member
0 Kudos

Hi ,

Inhouse produciton time & SMK (float after production) is already maintained as 0 .

Regards,

Sheik

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the actual available capacity means working Hrs. And then in FG BOM for SFG make lead time offset as - 30 min.

Please check and confirm

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

The actual available capacity is (Working Hrs) - 09:00 to 17:30 Hrs.

Also, tried with Opr Leadtime Offset as 30- MIN in FG BOM for SFG . With this setting , only the Reqmt date in Component overview - general data tab in FG Prod Order is displaying the time as 30 min before.

But , SFG prodn Order finish date/time remains unchanged(.12.05.09 17:30)

Regards,

Sheik

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

As your working hrs are up to 17:30 hrs so why that you are not getting the actual result that you want.

Please do the setting of avilable capacity as 06:00 to 06:00 hrs. in your work center and then create the new production order and check the result.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

I tried with setting of available capacity as 06:00 to 06:00 hrs , but system still schedules in same manner.

FG 13.05.09 22:00 14.05.09 06:00

SFG 12.05.09 22:00 13.05.09 06:00

Regards,

Sheik

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Sorry these are the order SFG and FG so it will not consider the the 'Lead-Time Offset for an Operation' in BOM Item basic data tab. This is for the components must be available before the start date of the operation -30 min before of operation.

For this you need to maintain the float this is only option for this.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

Floats serve as buffer between the Order - basic dates and prodn dates within an order.

pls explain how float will help in determining the Requirement date of components ?

Regards,

Sheik

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Float will not help to determining the Requirement date of components it will help to define order start and finish date.

BOM lead time offset will help you to determining the Requirement date of components for that you need to assign the component to operation in routing and maintain lead time offset in BOM.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

ya , its clear.

Thanks for your kind reply.

But , even with Operational Leadtime Offset maintained , during lead time scheduling , system is not calculating the provision date of the material components as required .

This is the problem.

Regards,

Sheik

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You must enter + value in days in BOM component details, operation offset time, for which component is needed in future. Then assign the component to Routing operation.

And in OPU3 and OPU5 in scheduling:- Adjust to operation date.

Also check this thread,

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear Brahmankar,

My requirement is SFG shd be available before the start date/time of FG 1st operation.

So i tried with negative value only.

These settings were already in place.

- Component is assigned to Routing operation and

- OPU3 & OPU5 - Adjust to operation date

Regards,

Sheik

Former Member
0 Kudos

Hi,

In case of backward Scheduling, as you are aware that the system schedules only from the Shift end time from Available capacity (17.30 hrs) in all cases. The 30 min offset between two operations of one production order can be achieved with the process of overlapping. But two different production orders in your case of SFG and FG overlpping is not possible to obtained as per your requirement. One way is to do the same with Capacity Levelling and if the number of orders are more then this process will be tedious to be carried out.

-Thaila Shree

Former Member
0 Kudos

Thanks Thaila.

So it is possible only through manual capacity levelling.But , as you rightly said , this will be a tedious process. Client wont accept.

Regards,

Sheik