Hi,
i would like to know the method to be followed in order to transfer the materials from one storage bin to another within the warehouse and also within a storage type.
Also i would like to know how to transfer the material from one storage type to another.
This topic has been discussed many times on SDN forum. You can use LT01 / LT10 for manual transfer. (whether storage type is same or not, doesn't matter)
Regards,
Csaba
Edited by: Csaba Szommer on Apr 28, 2009 6:07 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Csaba,
If we have to transfer 50000 pcs or we can say 50 Storage Bins together so what is the process and Tcode to send together.
Because in the LT01 & LT10 we can transfer one by one or if we take one storage type so it only take one storage unit for transfer.
so please give us a solution to transfer together.
Thanks & Regards
Shashank Dwivedi
As everyone has mentioned above, to manually create TOs to transfer stock, use LT01 w/ movement type 999. However, this method is limited to a single material at a time.
Depending on your scenario, you may want to set up storage type replenishment - where you regularly restock a smaller warehouse location from a larger one:
Example: Small warehouse section with customer counter service & larger warehouse where bulk items and bulk quantities are stored
Not sure if this is your scenario or not, but here goes:
Requirement is to use the "Large, small" picking strategy for the receiving storage type.
Material master records in that storage type need minimum and control quantities maintained on the WH2 tab
Run (or schedule) program RLLNACH1 to automatically create transfer requirements to transfer stock from bulk storage to the smaller storage type - and then, depending on your config, either stop as TR or automatically post os TOs.
Good luck
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If we have to transfer 50000 pcs or we can say 50 Storage Bins together so what is the process and Tcode to send together.
Because in the LT01 & LT10 we can transfer one by one or if we take one storage type so it only take one storage unit for transfer.
so please give us a solution to transfer together.
Thanks & Regards
Shashank Dwivedi
Please use movement type 999 and LT01...for SU management use LT09.
Regards
Kiran V Yarlagadda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kiran V Yarlagadda,
If we have to transfer 50000 pcs or we can say 50 Storage Bins together so what is the process and Tcode to send together.
Because in the LT01 & LT10 we can transfer one by one or if we take one storage type so it only take one storage unit for transfer.
so please give us a solution to transfer together.
Thanks & Regards
Shashank Dwivedi
you can use LT01 & LT 10
Regards,
Prashant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prashant,
If we have to transfer 50000 pcs or we can say 50 Storage Bins together so what is the process and Tcode to send together.
Because in the LT01 & LT10 we can transfer one by one or if we take one storage type so it only take one storage unit for transfer.
so please give us a solution to transfer together.
Thanks & Regards
Shashank Dwivedi
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.