on 04-28-2009 9:33 AM
Dear All,
In scheduling agreements, I have set tolerance limit 5% upper limit, for the customer (in CMR ) .
I have created order for 100 nos(total qty.) and for this ,there are 5 different schedules of 20 qty.each time.
My question is for every delivery I do on different dates of 20 each if I send 21qty (5% upper tolerance limit kept) system is not allowing ....
Can somebody guide please.
Umesh
Hello Friend,
Please set the indicator in the Partial delivery/Item field to 'D' (partial delivery allowed), this takes priority.