Hi Experts,

My questions are

a) What is direct procurement and what will be the process in CS and ECS?

b) What is the difference with Plan-Driven procurement and Direct procurement?

c) and When we order one material what will be the further process (Follow-o Documents,and Any SAP-MM) key points??

Please help me in this regard.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Please follow answers

a) What is direct procurement and what will be the process in CS and ECS?

Ans -

Direct procurment mean procument if direct material (production material)

b) What is the difference with Plan-Driven procurement and Direct procurement?

Ans - both the things are differant

direct procurement is normal procument cycle .. SC - PO - GR IV ..

after SC other doc can be created in back end depending upon the senario.

Plan driven procument is degined to get requirements from other back end system in sourcing cockpit directly, they does not require any approval flow in SRM as that of normal approch.

http://help.sap.com/saphelp_erp2005/helpdata/en/index_srmaddon.htm

c) and When we order one material what will be the further process (Follow-o Documents,and Any SAP-MM) key points??

Depending upon the senarios documents would be created in SRM or back end.

Here you should get all the relavant information about the follow on doc depending on senarios

http://help.sap.com/saphelp_erp2005/helpdata/en/index_srmaddon.htm

If you need further clarification please let me know