on 04-28-2009 8:43 AM
Dear all,
Could someone please let me know wht is difference between MTS and MTO scenario related to cost, settlement ,variance calculation and overhead.
Rgds
Hi,
MTS:- Costs will be settled aganist Production order
you have to issue Material aganist Product order
MTO:- Costs will be settled aganist sales order
you have issue material aganist sales order by using 261 E
Thanks
sreeni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Surendra,
Related to cost, settlement ,variance calculation and overhead there is no difference between MTS & MTO.
The difference lies with inventory control.
Hope this helps you.
SmanS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per my knowledge there is no difference in the dettlement process for both.
However, it is different for descrete and REM, as costs are booked on Production Order in Descrete and on Product Cost Collector in REM scenario.
Let the experts comment.
Regards,
Rohit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.