Dear Friends,

In report S_ALR_87013558, can anybody tell what is the column RemOrdPlan-Overall for ?

Some amount is showing in this column?

It will be very helpful if anyone can explain me the significance of each column.

Regards

R Panda

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Muzamil

Former Member
0 Kudos

Refer thread:

Regards,

Former Member
0 Kudos

Thanks for your reply. Could you please clarify the difeerence between planned, actual & commitment for PR & PO.

Regards

R Panda

Former Member
0 Kudos

Hi,

Planned cost is the cost your planning for materials,services,labor etc.

Commitment is created when you create PR and PO.SO PR and PO cost is commitment costs.

Actual costs is what you are actually posting like GI,Activity confirmation for internal services etc.

Muzamil

Former Member
0 Kudos

Thanks a lot for your reply.

Could you please clarify the following scenario.

Stage one---PR- Rs 1000

Stage two---PO- Rs 500

Stage three---GR- Rs 300

Stage four---IV - Rs 200

Please tell me what should be the RemOrdPlan-Overall after each stage

Please correct me if I am wrong.

Commitment----500

Actual----300

What should be planned in this case.

Regards

R Panda