on 04-28-2009 6:17 AM
i have give POC weitages to activities and scheduled the project
want to see the s-curse
can anyone tell me the path to find the S-Curve
Thanks in advance
Regards
surya
S-curve can be plotted for cost, work etc.,...if u wanna see cost vs period S-curve...then go to CN41, select PD or WBSE...Goto>period breakdown...it will take u to new screen where u will have Periods in LHS and Plan cost, Actual costs, Budget etc., in RHS...then click on any column say Actual cost then goto>Graphic>Period Breakdown....U will see period in x-axis and Actual cost in Y-axis...
Same can be done for Work also...U can follow the above steps in CNE5 also