In me52N there is a tab called Release strategy and in that there is icon .How is the icon set and based on what condition? How can we change it?

George

Accepted Solutions (0)

Answers (2)

Answers (2)

naimesh_patel
Active Contributor
0 Kudos

Hello,

If you want to define the release strategy, you have to define in SPRO.

the defination is like

Defines the release codes with which a purchase requisition item, a

complete purchase requisition, or a complete external purchasing

document must be released (that is, approved, or given the "green

light") and in which sequence release must be effected using these

codes.

For example, you may specify a certain release strategy for all purchase

requisitions whose value exceeds a certain figure.

Former Member
0 Kudos

Based on the config there will be somebody who will be able to release the PR, normally the release strategy is based on the value of PR, there could be multiple levels of Release(R1, R2, R3..)