on 04-09-2006 4:48 AM
In me52N there is a tab called Release strategy and in that there is icon .How is the icon set and based on what condition? How can we change it?
George
Hello,
If you want to define the release strategy, you have to define in SPRO.
the defination is like
Defines the release codes with which a purchase requisition item, a
complete purchase requisition, or a complete external purchasing
document must be released (that is, approved, or given the "green
light") and in which sequence release must be effected using these
codes.
For example, you may specify a certain release strategy for all purchase
requisitions whose value exceeds a certain figure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Based on the config there will be somebody who will be able to release the PR, normally the release strategy is based on the value of PR, there could be multiple levels of Release(R1, R2, R3..)
Regards
Anup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.