I have designed a release strategy with three characteristics:

This is what I entered in characteristic

1.PRQuantity with table name MEREQ3211GRID and Field :MENGE

2.PRmaterial # with table name RMMG1 and Field :MATNR

3.PRPlant with table name RMMG1 and Field :werks

the value for PRQuantity is >= 10000,000.

Also, I have set the indicator for (allow interval) in characteristics

Classes, procedure with classification, Release startegies are all proper.

I am getting the Release startegy tab in PR, but the problem is when I adopt a PR to create a PO with PO quantity >=10000, the release starategy gets picked up, which is perfect but it is also getting picked up with PO Quantity <=10000.

I dont understand why is it getting picked up for <=10000..Please suggest!!

Thanks in advance!!