on 04-27-2009 11:47 AM
Gurus,
I am trying to create stock for returnable packing material, T-code : MB1C.
I got following error -
No SLED processing for material 3923. Data entered is cancelled
Message no. 12020
Please suggest solution.
Regards,
Ashish
hi
In MMR for the material in the tab PLANT DATA /STOR1
maintain thr values in the fields
Period Ind. for SLED
Max. storage period
Min. Rem. Shelf Life
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rithvika,
Thank you very much for your quick reply as usual.
I have maintained data.
While creating stock in MB1C,
I got following error - should I stop to go futher from this point. I understood the concept.
Account determination for entry INT BSX ____ ___ 3050 not possible
Message no. M8147
Diagnosis
The system did not find an account for this transaction. This means that
the account determination for key INT BSX ____ ___ 3050 is not
maintained in MM Customizing (Valuation). The key is made up of:
o Chart of account
o Transaction key (= Posting transaction)
o Valuation grouping code
o Account grouping code
o Valuation class
System Response
The system cannot update a G/L account for this transaction. You cannot
post the transaction.
Procedure
Contact your system administrator.
If you have the authorization, check the Account determination in
Customizing for Valuation.
Proceed
Note
The relevant posting transaction can be found in Table T030A.
Hi
To eliminate this error two things you have to do
1. In t code OBYC double click BSX and give chart of accounts as INT and enter
There for the valuation class 3050 please check whether have you maintained proper debit and credit accounts
2. In t code OMWD the valuation grouping code 0001 has been assigned to your plant that needs to be checked If not assigened please assign it
Also in MMR please check in sales general plant/ data the settings regarding Returnable Packing are maintained
Regards
Raja
Dear Mr. Raja,
Thank you for your quick message.
-> T-code : OBYC
I have not maintained debit/credit account.
For valuation class 3050 -> which G/L a/c I have to choose.
This could be very basic question but I have no knowledge of accounting/finance.
-> T-code : OMWD
There is following assignment i found
Val.Area + CoCode + Company NameChrt/AcctsVal.Grpg Code
There is no assignment with plant.
Please help me.
Regards,
Ashish
Hi
I beleive that you are learning and the exercise that you are doing now is not a real time scenario
Hence i am suggesting you this
If it is a real time these t codes are handled by MM people with FI help and SD consultants has no role here
For OBYC there will be some other GL account entries maintained for valuation class like 7920 the valuation class which is used for finished goods
I mean there must be some entries in both debit and credit column
Assign the same GL accounts for 3050
Follow the steps given in last post
For OMWD Valuation area is your plant and put your company code chart of accounts as internal and then valuation grouping code as 0001 (note 0001 is the standard valuation gropuping code) and assign this
Regards
Raja
Ashish,
SLED settings are in PLANT/Storage tab of Material management screens(mm02). Manufacturing and BB Dates are calculated on this data that you set. Please check your settings in this tab of MM02
Check that
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.