hi,
I want to know how i can use vaule in remorderplan for a WBS
Regards,
Kalpesh
Remaining Order Plan is used in different scenarios of Budget Control.
For example,If the business requirement is that after budgeting even the plan should not be increased beyond the budget,then we make the rem.order plan to be a prt of the assigned values,so that you cannot increase the plan.
But if the business requirement is like after budgeting the system should permit increase in plan values but restrict the commitments to get generated below the Budgeted value,then rem.order plan will not be a part of the assigned values.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to make plan cost zero, follow as under for existing projects:
Remove the planning indicator first in OPSC.
Make plan cost zero by making price zero for activity.
Again put planning indicator in OPSC.
Now again enter price for activity.
If you can not make price for activity 0, don't use it.
SSanjay