cancel
Showing results for 
Search instead for 
Did you mean: 

lead time

Former Member
0 Kudos

Dear friends,

Is there any report in SAP LE which can give the total lead time for delivery of materials from the plants to the destinations(customer)

Your valuable reply is highly appreciated.

Regards,

Sampath

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Sampath,

I am not aware of such a report.

The duration of time scheduled in a Sales order between the shipping point and the destination is carried in the Sales routes (configuration transaction OVTC). The routes that your company uses can be determined in a number of ways. Information (including duration) can be seen in Table TVRO. Information concerning determination (which route is associated with a source-destination pair) are usually contained in table TROLZ. This configuration is in IMG>SD>Basic Functions>Routes>Route Determination>Maintain Route Determination.

If you actually interested in the 'lead time', which also includes manufacturing/procurement time, Pick/Pack Processing time, etc, this is a bigger task. More data needs to collected.

In either case, I believe you will have to commission your ABAPers to create a Z report.

Regards,

DB49

Former Member
0 Kudos

Dear DB,

Thanks for your reply. I will check for the same.

Regards,