on 04-25-2009 2:02 PM
Hi, experts,
Can any please tell me using CATs ,whether we can perform following activity---
1. Time confirmation without goods movements.
2. Time confirmation with TECO of PM orders
3.Capacity planning of PM orders.
rgds
rajib
Hi,
pl note that cats is cross application time sheet.so answers to ur questions are:
1.Time confirmation without goods movements......possible
2. Time confirmation with TECO of PM orders........only time confirmation possible,no TECOing
3.Capacity planning of PM orders........not possible.
This functionality refers to posting time sheet data otrtime entries to multiple applications,key figures or service entries for MM area etc.
regds,
atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
CATS are basically used in Customer service Module. Where u send your employee to customer site, and u need to bill the customer, for the hours he has worked, over time...
you will be maintaining diff cost for diff employee... it differes from cader..
It is done during time confirmation only...
Else u need to login via the employee sap login... go to human resourse... enter the hours of work for the particular order... and save it..
This will be send to ur boss.. he has to approve it and then it will be billed...
- Pithan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.