Hi, experts,
Can any please tell me using CATs ,whether we can perform following activity---
1. Time confirmation without goods movements.
2. Time confirmation with TECO of PM orders
3.Capacity planning of PM orders.
rgds
rajib
Former Member replied
Hi,
pl note that cats is cross application time sheet.so answers to ur questions are:
1.Time confirmation without goods movements......possible
2. Time confirmation with TECO of PM orders........only time confirmation possible,no TECOing
3.Capacity planning of PM orders........not possible.
This functionality refers to posting time sheet data otrtime entries to multiple applications,key figures or service entries for MM area etc.
regds,
atul