Dear All ,
WHENEVER I am opening my existing project , first activity shows the start date of project as today's or current date and whole of my scheduling is getting disturbed.
What may be the reason ?
Regards,
Check customisation OPU6 - "scheduling type" , "start in past" parameters...
rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In OPU6 set the "Start in the Past" as 999 then schedule.