on 04-24-2009 9:24 AM
Hello All,
I had given my released activity to the basis team for transport and they reported 'assembly failed' error due to broken dc's.
Any clues on this error ?
Hi Parama,
Check if there are any dependencies for that DC, if so you need to follow the order according to the dependency order.
Also check the following link to fix the Broken DCs problem.
http://help.sap.com/saphelp_nw70/helpdata/EN/46/14fa07c15214dce10000000a155369/frameset.htm
Thanks & Regards,
Jhansi Miryala