reg completion of PI sheet

Dear all,

When should we complete a PI sheet in a process order.

Thanks in advance



There is no such restirction on PI Sheet completion due to any process order status.But Completion of PI Sheet may effect the Status of Process order.For example you can can not set deletion flag or set order status CLSD untill status CRCR chane to CRFI.