reg completion of PI sheet

former_member1355332
Participant
0 Kudos

Dear all,

When should we complete a PI sheet in a process order.

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

There is no such restirction on PI Sheet completion due to any process order status.But Completion of PI Sheet may effect the Status of Process order.For example you can can not set deletion flag or set order status CLSD untill status CRCR chane to CRFI.

Regards,

Dhaval

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You cannot "complete" a PI Sheet if there are open entries i.e. if fields are not locked you cannot "complete" a PI Sheet.

However, even with open entries you can "Technically Complete" a PI Sheet.

You can complete the PI sheet there are no open entries