on 04-23-2009 2:51 PM
Hi, all,
Through looking at related threads here, I see I can do this by changing c_finaa-nacha = 'I' in FM SAMPLE_PROCESS_00002040. But I see value range for field nacha only have 1--Printout 2 Fax in our system, and don't see the value Iemail. We are far ahead of package 21 for release 4.6C. How can I add value I -- email to that field? Do I need to do configuration in IMG? Thanks.
Meiying
Edited by: Meiying Yang on Apr 23, 2009 5:44 PM
please refer sap note 521587
407827
836169
Regards,
Ravi
Edited by: Ravi Sankar Venna on Apr 23, 2009 5:12 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Ravi,
Thanks for the reply. I have read those SAP notes. But my question is, my our system, the value range for field NACHA only has two values ( 1 = print, 2= FAX), and don't have value I = email. If I = email is not in the value range, I am worrying about FM would not pick it up. How I can add I = email to the field NACHA value range? Thanks.
Meiying
"I" will be automatically updated in the structure if the Vendor master has an email address maintained. The include RFFORI06 in the payment program will take care of it. The priority of the communication preference will be as follows:
1. Email
2. Fax
3. Print
Program first checks for email address, if it's there will send an email. If not then it will check for Fax no., sends fax if it finds one and if both are not maintained it will print the Payment Advice.
The Business Transaction Event has to be defined in t-code: BF44 as below:
Process Function Module Product
00002040 Z_PAYMENT_ADVICE_FAX ZFAX
00002050 Z_PAYMENT_ADVICE_EMAIL ZFAX
Also need to make sure that the user profile has his Internet Mail id maintained under Communication in the Address tab (SU3).
Hope this helps.
Regards,
Ashok
For standard 00002040 FM, you need to put the email address on the general data tab page of vendor master.
Before, generating the emails, your basis must have configured the SCOT
You can see the mail triggered at SOST transaction code.
In DEV and QAS system, normally the gateway must have been closed due to security reasons. The mails come up to SOST and fail there. But, you can ensure at least the mail is being triggered.
Regards,
Ravi
Hi Meiying,
The field might be suppressed so you are not seeing it in the Vendor master.
Please check the following config:
SPRO->FA->AR&AP->Vendor Accounts->master records->Preparations for creating vendor master records->Define Account Groups with Screen Layout (Vendors)
Select the relevant Vendor Group and double click the Field Status for General Data and then select the details for Communication, make the fields Internet address and Internet mail address as "optional".
Regards,
Ashok
Thanks, Ashok,
I have figured it out yesterday. But sounds like the email is still not triggered. I have entered email to a vendor and saved. And I created a vendor invoice. I copied function SAMPLE_PROCESS_00002040 to my own and made change c_finaa-nacha = 'I'. And use FIBF registered it according to somebody's instruction in other thread. But after I ran F110, I did not see email is trigered. And I don't see field being automatically updated. Do you see I miss some steps? Thanks.
Meiying
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.